Spans Envirotech Logo
Case Study

KRBL Limited

Industry: Agro-Processing - Basmati Rice Manufacturing• Location: Ghaziabad, Uttar Pradesh, India

The Challenge

Ageing ETP Failing Under Peak Production Loads

KRBL Limited is India's largest basmati rice company and one of the world's leading rice exporters, with iconic brands including India Gate, Unity, and Nur Jahan. Operating state-of-the-art rice milling and processing facilities in Ghaziabad (Uttar Pradesh), Dhuri (Punjab), and Gautam Budh Nagar, KRBL processes over 1 million tons of rice annually for domestic and international markets across 90+ countries.

The company's rice milling, parboiling, and packaging operations generate substantial process wastewater from paddy washing, equipment cleaning, and utility systems. The existing ETP at their Ghaziabad facility used outdated trickling filter technology that was underperforming and struggling to meet Environmental Protection Act, 1986 discharge standards during peak production at 650 m³/day (BOD: 1,300 mg/L, COD: 3,000 mg/L). A comprehensive upgrade was required — but it had to be executed without disrupting continuous rice processing operations.

Key Issues:

  • !Existing trickling filter technology underperforming and unable to consistently meet discharge standards during peak production
  • !Zero-downtime requirement — any production shutdown would result in significant financial losses and impact international supply commitments
  • !KRBL had substantial capital invested in existing civil structures that needed to be retrofitted rather than demolished
  • !Water reuse pathway required — treated water needed to meet quality suitable for non-potable reuse applications
  • !Investment budget of approximately ₹85 lakhs required maximum performance improvement with superior ROI

The Solution

Trickling Filter Converted to High-Performance Two-Stage MBBR System

Rather than proposing complete replacement, Spans Envirotech conducted a thorough assessment of existing infrastructure, wastewater characteristics, and operational patterns. We identified that the core civil structures were sound and could be repurposed, but the treatment process configuration needed fundamental transformation. Our strategy: convert the outdated single-stage trickling filter system into a high-performance two-stage aerobic biological treatment (2AB) system optimised for rice processing wastewater.

The most innovative aspect was transforming the existing trickling filter into a modern Moving Bed Biofilm Reactor (MBBR) and high-rate aeration tank — removing trickling filter media, installing high-efficiency diffused aeration systems (1,100–1,200 m³/hr capacity), and configuring the reactor to operate at high MLSS (6,000–8,000 mg/L). The retrofit was executed in carefully planned phases to ensure KRBL maintained wastewater treatment capability throughout the upgrade, with no impact on rice processing operations.

Technologies Deployed:

Two-Stage Aerobic Biological Treatment (2AB)Trickling Filter to MBBR ConversionStage 1: High-Rate Bio-Sorption Reactor (MLSS 6,000–8,000 mg/L)Stage 2: Polishing Oxidation Reactor (MLSS 3,500–4,000 mg/L)Diffused Aeration Systems (1,700–1,800 m³/hr total)Dual Clarifier with Return Activated SludgeNutrient Dosing & Sludge Dewatering Beds

Implementation Timeline:

1

Phase 1: Audit & Redesign Strategy

Conducted a thorough assessment of existing infrastructure, wastewater characteristics, and operational patterns. Identified that core civil structures were sound and could be repurposed. Developed a phased retrofit plan to enable continuous operation throughout the upgrade.

2

Phase 2: Stage 2 Upgrade (Existing Aeration Tank)

Installed new equipment and enhanced aeration capacity (600 m³/hr) in the existing aeration tank while the original system continued operating. Gradually shifted treatment load to the upgraded Stage 2 reactor.

3

Phase 3: Stage 1 Conversion (Trickling Filter to MBBR)

Executed trickling filter conversion during a planned maintenance window — removing old media, installing high-efficiency diffused aeration systems (1,100–1,200 m³/hr), and configuring for high-MLSS bio-sorption mode at limiting dissolved oxygen.

4

Phase 4: Commissioning & Optimisation

Commissioned integrated two-stage system and optimised performance through controlled startup and biological acclimation. Conducted full-load performance testing across all parameters. Total project completed in 6 months with zero production downtime.

The Results

95%+ Removal, ₹1+ Crore Saved, Zero Downtime

95%+

COD Removal

COD reduced from 3,000 mg/L to <150 mg/L — consistently meeting EPA 1986 Schedule VI standards

98%+

BOD Removal

BOD reduced from 1,300 mg/L to <25 mg/L, well below the 30 mg/L discharge limit

₹1+ Cr

Infrastructure Saved

Existing tanks, clarifiers, and civil structures salvaged through creative retrofitting

₹85 Lakhs

Total Investment

Delivered versus potential ₹2+ Crore for new construction — a fraction of the cost

Zero

Production Downtime

100% operational continuity maintained throughout the 6-month upgrade period

100%

Compliance

Zero regulatory violations since commissioning, including during peak harvest season

Spans Envirotech delivered what other vendors said was impossible — a complete ETP transformation without stopping our rice milling operations. Their creative conversion of our trickling filter into a high-performance MBBR system was brilliant engineering. We salvaged over ₹1 Crore in existing civil works, completed the project in half the time, and achieved 95%+ COD removal. Most impressively, they executed the entire retrofit without a single hour of production downtime. Spans proved that smart retrofitting beats new construction when you have the right engineering partner.

Manoj Kumar

Engineering Manager, KRBL Limited, Ghaziabad

Achieve Similar Results for Your Facility

Let us design a custom solution tailored to your specific needs.